The City of Summerside has partnered with international tech giant Samsung to test a massive solar energy battery.
The pilot programs’ proponents are touting it as a first in Canada.
Samsung Renewable Energy Inc. and city made the announcement Thursday. The project will coincide with a solar energy project the city had previously announced for Credit Union Place (CUP) in an effort to shrink the facility’s massive electrical bill. The city pays more than $380,000 annually to power the facility and the battery and solar panels are expected to save the CUP a little more than $100,000 annually.
Thursday’s announcement was the culmination of a lot of hard work by a string of people from P.E.I. to Korea, where Samsung is based, said Summerside Mayor Bill Martin.
“This was a year in the making … our agreement for this project is 510 pages long, for Phase I. So it took a lot of work, a lot of back and forth. So I would say (I’m) a combination of extremely excited, proud and relieved,” said Martin.
Martin also said that this is phase one in what could be a three-part project with Samsung. It all depends on how this initial pilot project goes, but the two parties have signed a memorandum of understanding regarding all three phases.
Phase one involves constructing a shipping container-sized battery and integrating it into CUP’s electric system. The battery will be fed power from 1,300 solar panels the city plans to build on a portion of the facility’s current parking lot. The battery will store excess energy and pump it into the building during peak use hours.
To accommodate the build, one of the outdoor beach volleyball courts will be moved. The city does not expect to lose any parking spaces as a result of the solar panels.
Phase 2, if it happens, will include the construction of a new solar/wind farm. This phase would bump the percentage of electricity the city gets from renewable sources from 46 per cent to 70 per cent.
Phase three would include investment in more electric pilot projects, such as infrastructure for electric vehicles and a smart grid system.
Martin said he expects Phase 1 to be completed sometime this fall.