The largest battery storage system in the world will also be one of the fastest constructed in history.
In August, San Diego Gas & Electric tapped energy storage company AES to install two energy storage projects totaling 37.5 MW, 150 MWh. When completed, the larger, 120 MWh project is expected to be the single biggest lithium ion battery in service on a utility grid in the world.
Both battery facilities are expected to be online by the end of January 2017 — nothing short of miraculous in an industry where deploying assets, especially newfangled technologies, can take years.
And the companies are not alone. Southern California Edison and Tesla announced a 30 MW, 80 MWh project in September that is expected to be online even sooner, and will be the largest operating battery for a time.
The accelerated deployment comes in response to an unprecedented shortage of natural gas for electricity generation in southern California. Last October, a leak at the Aliso Canyon gas storage facility outside Los Angeles caused it to be shut down, constricting fuel supplies for area plants.
Fearing blackouts, the California Public Utilities Commission quickly mandated a series of mitigation measures, including an expedited procurement for local energy storage resources. The more renewable energy that can be stored during the day, the reasoning went, the less need to fire up fossil fuel generators as electricity demand increases in the evening.
The CPUC order directed the utilities to identify storage projects that could be sited, constructed and put into operation in only a few months. Though the regulators said storage resources must be “cost-effective” compared to other local capacity products, no pricing details for the projects have been released.