The requirement of nine hours of energy storage duration at a project touted as a possible replacement for a new natural gas plant in California makes it tough for the newer technology to compete on cost, an analyst has said.
Back in June, the California Independent System Operator (CAISO), which is responsible for much of the state’s high voltage transmission lines, ensuring security of electricity supply and keeping costs to ratepayers as low as possible, agreed to investigate alternatives to building a 262MW gas power station.
CAISO’s study on the Puente Natural Gas project came about after the regulator, California Public Utilities’ Commission (CPUC) approved it as a solution to fears of capacity shortfall that will result from the planned retirement of some 2,000MW of local generation assets by 2020 under environmental rules. After utility Southern California Edison (SCE) and developer NRG Oxnard Energy Center were given approval for the plant, California Energy Commission agreed to an offer made by CAISO to consider alternatives.
Nine-hour requirement adds big cost
The CAISO study was published earlier this month. While finding it feasible for energy storage – as well as a combination of energy storage and synergistic technologies such as demand-side response – to be available to deliver the required capacity, there were some drawbacks.
Energy storage was found to be a more expensive alternative to building a new natural gas plant to meet local capacity requirements by about US$500 million under two of the main scenarios modelled and investigated by CAISO. Capital costs for the development of “Incremental distributed resources plus grid connected battery storage” were estimated at US$805 million. A new 262MW natural gas plant was estimated at US$299 million capital cost.
“In scenario 1 you have two, 9-hour systems. That’s what’s really driving the cost here,” Daniel Finn-Foley, energy storage analyst at GTM Research, said.
“For utility-scale energy storage, the sweet spot that we’re seeing right now is around the 4-hour system. As you keep adding duration to these systems, you’re increasing the cost but you’re not actually increasing the power it can output. So an energy storage system that can provide 60MW for four hours is still providing 60MW even if the duration is increased to nine hours, but it now costs a lot more. That’s one of the things driving this pretty steep cost increase here.”
Recent Comments